Sayed Al-Awseaa Project


Cool web Image

Survey, Implement, Design, Supplly, All require for this project hardware / software

We finished a big projects in Visitor city of Kerbala City :

1- CCTV ( Axis)
  • Fiber Optic (24 core) cabling work more than 3500 M with about 20 joining points for main and branches cabinets
  • Installed 17 Branches Cabinet Racks and 2 main control racks with all required systemization STP Cat 6 Cabling work.
  • Installed 18 Brocade ICX switches (POE and Fiber Ports ) in all racks with required configuration.
  • Installed about 87 outdoor IP Cameras (P 1357) & about 8 outdoor Camera Speed Dome + Bracket ( Q6045-c) with all required
    configuration along the Visitor city project.
  • Installed about 96 Indoor cameras (Camera doom indoor P3214-Ve) with all required configuration along the Visitor city project.
  • Installed 10 NVR 's with 32 Channel with all required configuration in control racks.
  • Installed 8 LFD Samsung 46 inch screens.
  • Power cabling work with more than 1700 M between 19 racks all required configuration along the Visitor city project.
  • Installed the control room with 3 PC clients.

2- Telephone system PBX NEC project
  • Fiber Optic (48 core) cabling work with more than 2050 M with about 24 joining points for main and branches cabinets.
  • Installed 52 Branches Cabinet Racks and 1 main control racks with all required systemization STP Cat 6 Cabling work and Fixing                      Keystones inside Buildings and rooms along the city.
  • Installed 54 Cisco switches (48,24,& 8 )(POE and Fiber Ports ) in all racks (Main and Branches Racks) with required configuration.
  • Installed PABX VoIP model NEC SV9100, (496 IP line Internal, 8 IP External, 16 Analog Internal, 8 Analog External).
  • Operation and Programing the PBX with about 530 different IP Telephones.

3- Televes TV – systems
  • Installed 5 – RF Televes TV systems (20 channel ) in 5 Buildings and in each Building about 40 TV points.
  • Operation and configuration the RF Modules and Amplifier modules in all systems .

4- Internet and data – systems
  • Installed 5 – Internet systems in 5 Buildings and in each Building about 80 Keystones points.
  • Operation and configuration the Cisco Switches and routers and reach services for all rooms.




You Can Visit Us On Our Location Below

Iraq

Baghdad/ Al Karada Kharidge, Al-Hurya Square

Al-Hariri Building - 3rd floor



Kerbalaa/ Hay Al-Iskan, Al-Hayat Building - 3rd floor



Lebanon

Beirut/ Bir Hassan, New Airport Highway

Al-Turath Bldg. |1st Floor



00 (964) 7901289370

Sat to Thi 8:30am to 4 pm



00 (964) 7806612678

Sat to Thi 8:30am to 4 pm



info@atlasgis.net

Send us your query anytime!